Mon: Arrived at
Trial and error lead to success on Mikes flooring job. Two boxes needed to complete the job.
The engineers will create a great corner area with a stained plywood side, stained to match the cabinets.
Tues: The right tools make all the difference, ah yes! Once we had them we hit full speed.
Marvin and Bruce worked on kitchen cabinets, upper and lower. Solid!
Mike continued the not-so-easy task of installing laminate flooring backward. (A method he unfortunately inherited from a previous volunteer. This method requires frequent mental health breaks).
Ina Marie and pat began the staining of cabinet doors. At the end of the day upper cabinets were indoors, stained and flooring finished (and documented on film).
Wed: Arrived around
Ina stained kitchen cabinets and with Pat varnished cabinet doors. Cabinets will be varnished tomorrow.
Bruce and Marvin installed the lower corner cabinet and trim all around. It is looking GREAT!
By
The afternoon resulted in Mike’s completion of one side railing on the front. Other side started and will be completed tomorrow. Thanks to the expertise of our resident engineers
Tomorrow